Bank of America - Sacramento

The Bank of America Sacramento Branch process was a 3 phase project. When working on this project Summer Systems provided temporary air during the renovation process. Summer System's jobs scope included cable rack installation, new ceiling T bar grid, new concrete slabs, complete mechanical platform, new roofing installation, fire and safety features, and DDC control systems. Three 25 ton Aaon HVAC units were provided and consisted of a variable air volume loop design system.